🚧🛤️ All smiles from Engco's Senior Project Engineer, Thomas Costa!

Thomas's hard work planning, gaining access & permit approvals, design coordination, procurement, resourcing, and on-site management was put on display during a critical 96-hour rail shutdown with Djilang Alliance resulting in incredible results summarised below:

✅ Installation of 170 metres of Combined Service Route (CSR); approximately 1,000 metres of conduit in preparation for Signalling Infrastructure.

✅ Installed 12 x Signalling /Comms pits.

✅ Constructed 110 metres of above ground route.

✅ Installed 1 x concrete LOC box foundation for future Signalling Equipment.

✅ Installed 50 metres of perimeter fencing providing safe access for future maintainers.

✅ Conducted structural assessments on existing infrastructure.

✅ Constructed 2 x undertrack CSR crossings.

✅ Multiple connections into existing LOC boxes & Signalling/Comms pits.

Congratulations

Thomas Costa and a big extended thank you to the dedicated team for their efforts which included All Civil Australia Pty Ltd, QEST Infrastructure Pty Ltd, Realsurv Engineering Surveyors